Sunday, 31 July 2011
the roof
The roof is now felted & battened.
Here is the next 3 weeks' worth of jobs:
Windows & doors to be fitted (thanks to John& Leslie at Palladio)
Soffits & fascia boards (Lee & the gang will be back)
Tiling
Brickwork
Also during that time, Andy & the digger will be back to install the rainwater harvesting tank.
Thanks are due at the moment to Richard & Lou at Accent Lighting in Daventry for all their help in planning our lighting.